EMERGENCY MAINTENANCE

Our datacenter team will be replacing one of the PDU (Power distribution units) at the server11 (207.44.244.81).
There will be a downtime maximum for 2 hours.
Planned downtime will start at FRIDAY, JUNE 18, 2004, 01:00 AM CENTRAL TIME (GMT -06:00)

After an extensive review of our entire power supply and distribution system after the damage on Saturday we have found one PDU (Power distribution unit), the equipment that sits between the UPS and client servers, that needs significant repair and/or replacement. The parts required, including a cold spare, are on site and standing by.

Though this unit is still functioning, initial evaluations and scans indicate that it is not operating within acceptable parameters. We feel that there is a greater risk by NOT doing the maintenance and/or replacement as soon as possible. Being in control of the process (being proactive) would be much better than being reactive in an emergency situation.

Thanks for your continued understanding.